Company:
Cool Awnings Auckland,

Project Details

Fabric 1

Atmosphere mesh 1%
Producer: OTHER
Supplier: Shann New Zealand



Please describe the project specifications

The customer wanted us to provide a solution for glare coming in from 6 large north facing windows at a busy public train station. The windows were on the first floor and while they were mounted within an aluminum frame we did not want to mount directly into them and risk breaking the large, 10mm thick panels of glass and due to the suspended ceilings we did not have easy access to install directly into the mullions. As there was no access to control the curtains by gearbox or spring, they had to be motorized, with control from the ticket office. We decided a wire guided system would work best and designed a channel to mount the curtains at the top, which sat over the mullions, which was preassembled to save time on the install.


What was the purpose of this project? What did the client request?

The ticket office within the busy train station was getting blasted by the mid to late afternoon sun. It was directly in their eyes while they were trying to serve customers and they were very uncomfortable. Auckland Transport contacted their glass contractor who were unable to directly provide a solution, and they approached us for options. We were able to provide them with a solution to block the worst of the glare.


What is unique or complex about the project?

As this installation was within the busy train station it had to be after 7pm and before 5am, Sunday to Thursday. There was also a lot of attention to the site so all the T’s had to be crossed and I’s dotted for health and safety.
The curtains were to be mounted 6m high, over the first floor glass. The thick existing glass panels were mounted into aluminum frames that were not attached at the top, only left and right, leaving a gap for us to try a new option for mounting – channels! We manufactured a channel to fit over the customer’s mullion, and onto this channel we had pre-installed the curtain to enable quicker installation. However, as the curtain was a motorized and was to be mounted on the inside of the train station windows they were very heavy. As we could not get a scissor lift high enough to mount from the inside, due to the suspended ceilings, the installers had to install them from the outside, and over the top of the mullion off of platform ladders. Our biggest concern was that they would drop the units over the top and onto the floor 6m below, so we had a support team working on the inside, and they were also responsible for doing the bottom fixings.
Access to the outside was via an extension ladder through a small “hatch” which measured approximately 600 x 1000mm, to a narrow ledge. In one direction was the glass wall and the other was a glass awning, and the ledge was only wide enough for the ladder. We had to pass the ladders and awnings up to the boys working in the area in backwards order, as there was no room to maneuver.


What were the results of the project?

The PVC mesh blocked the worst of the glare and the ticket agents were once again comfortable in their work and the glass company were able to keep a big customer happy.


Content is submitted by the participant. IFAI is not responsible for the content descriptions of the IAA award winners.